Project information

  • Project: sudan
  • Client: Sedic

Project Details

al sudan for rebar rolling:
-installing & commissionig for the rebar rolling mill.
-maximize the prober porductivity five years to reach 3 times the design rate of the mull.

-adjust the optimization mode for both the cropping shears to achieve the maxmum yield for the poroduct.
-upgrading for the scada wonderware v7.11 version 8.
-also upgrading the ows from ver.4.5 to ver.5 .